Billings Logan International Airport Passenger Loading Bridges

This project included the replacement of four (4) passenger loading bridges and installing one (1) new bridge.

The existing bridges and their foundations were removed.  New concrete cast-in-place foundations were installed, electrical power was upgraded and the new bridges were installed.

The new bridges are ‘joystick’ controlled and fully electronic.  Each bridge included its own roof top unit providing heating/cooling to maintain a comfortable temperature within the bridge.