Park II Addition

The project scope included a 6-tier parking structure with a bank drive-through facility on the ground level. This new project ties into the existing parking structure. Park II spans the city alley, maintains a 15 foot head height clearance and covers approximately ¾ of a city block.

The time frame required continual operation through the winter months. Several 10,000 square foot slab pours had to be enclosed and heated at their 30-50 foot elevated heights for work to progress on schedule.